Experience

Client: Main Roads WA
Road and Bridge

Great Northern Highway Ord North Upgrade Stage 1 & 2

Design and construction of road widening, overlays and construction of new highway including the installation of culverts, replacement and extension of the existing drainage system to address excessive wear and to improve driver road safety.

Project Information
  • Client
    Main Roads WA
  • Sector
    Transport
  • Value
    60m
  • Location
    Western Australia
  • Contract Model
    Construct
  • Completion Date
    2019-2022

Structures: Design and construction of new Bridge GNH over Tickalara Creek including approach works and demolition and removal of the existing Bridge. Design and construction of new Bridge GNH over Frog Hollow Creek, including approach works and demolition and removal of the existing Bridge. Further works include re-surfacing of Spring Creek Bridge No 1445 deck and upgrading of the existing traffic barriers at approaches and departures to the bridge.

The upgrade will provide a higher level of serviceability, including full seasonal access.

The Ord River North Project is located near the town of Warmun in the Shire of Halls Creek in Western Australia, approximately 3,000 km northeast of Perth by road and 200km south of the Kununurra town site.