Experience

Client: KCGM
Earthworks

Fimiston Haul Road Construction

WBHO-I completed the construction of a 5.1km TSF Haul Road from the Eastern Waste Rock Dump Extension to the Kaltails and Fimiston II Tailings Storage Facilities (TSFs) including the construction of a major floodway crossing, LV/HV intersection and controlled railway crossing.

Project Information
  • Client
    KCGM
  • Sector
    Resources
  • Value
    4.5m
  • Location
    Goldfields, Western Australia
  • Contract Model
    Construct
  • Completion Date
    2019-2020

Delivery of the project saw some complex obstacles overcome through early involvement and critical risk identification with regards to design and intended execution. WBHO-I worked closely with the client’s design team to offer constructability advice. This early involvement was vital in ensuring the project proceeded and ensured accurate cost and quantity control.

WBHO-I carefully managed the interface with a major Interstate freight rail line over which the new haul road was to be constructed. WBHO-I implemented effective rail traffic management to ensure the works was able to continue with as little impact as possible. This initiative was well regarded as it ultimately provided a more long-term alternative while a more comprehensive redesign of the rail crossing control system was undertaken.